(RR-25-10) Study on the Development of an Ex-post Evaluation Methodology for PPP Roads
- Date
October 31 2025
- Authors
KWON Hyug,KIM Beom-il,CHO Yun-ji
- Page(s)
2 page(s)
Abstract
This study aims to establish a post-investment evaluation framework for privately financed toll roads in Korea, particularly under the recently introduced profit-sharing BTO-a model. While Korea has advanced its private investment system through the abolition of the Minimum Revenue Guarantee (MRG) and the introduction of feasibility and VfM assessments, current appraisal practices remain limited to the pre-construction stage. As toll road projects operate over several decades, discrepancies between ex-ante estimates and actual operational outcomes cannot be verified under the existing system.
To address this gap, the study proposes an ex-post VfM evaluation conducted after project completion, using actual operational data. The proposed framework updates the assumptions used in the ex-ante VfM analysis—such as demand, costs, and revenues—with real performance data, enabling a more accurate comparison between the Public Sector Comparator (PSC) and private alternative (PFI). The study develops a detailed methodology for estimating government payments under both PSC and PFI options, including risk-sharing adjustments under BTO-a. A case application using an operating BTO expressway demonstrates that actual traffic volumes significantly influence VfM results, highlighting the importance of performance-based updates.
The study also reviews institutional constraints, noting that the Construction Technology Promotion Act’s post-evaluation is unsuitable for PPP projects. Accordingly, it proposes legislative amendments to the Toll Road Act, introducing mandatory ex-post VfM evaluation when government risk-sharing payments are triggered. The results are expected to strengthen transparency, minimize unnecessary fiscal expenditure, improve long-term project governance, and enhance public trust in PPPs. The proposed system ultimately supports a virtuous cycle in which post-evaluation findings are fed back into future PPP appraisal and management processes.
This study aims to establish a post-investment evaluation framework for privately financed toll roads in Korea, particularly under the recently introduced profit-sharing BTO-a model. While Korea has advanced its private investment system through the abolition of the Minimum Revenue Guarantee (MRG) and the introduction of feasibility and VfM assessments, current appraisal practices remain limited to the pre-construction stage. As toll road projects operate over several decades, discrepancies between ex-ante estimates and actual operational outcomes cannot be verified under the existing system.
To address this gap, the study proposes an ex-post VfM evaluation conducted after project completion, using actual operational data. The proposed framework updates the assumptions used in the ex-ante VfM analysis—such as demand, costs, and revenues—with real performance data, enabling a more accurate comparison between the Public Sector Comparator (PSC) and private alternative (PFI). The study develops a detailed methodology for estimating government payments under both PSC and PFI options, including risk-sharing adjustments under BTO-a. A case application using an operating BTO expressway demonstrates that actual traffic volumes significantly influence VfM results, highlighting the importance of performance-based updates.
The study also reviews institutional constraints, noting that the Construction Technology Promotion Act’s post-evaluation is unsuitable for PPP projects. Accordingly, it proposes legislative amendments to the Toll Road Act, introducing mandatory ex-post VfM evaluation when government risk-sharing payments are triggered. The results are expected to strengthen transparency, minimize unnecessary fiscal expenditure, improve long-term project governance, and enhance public trust in PPPs. The proposed system ultimately supports a virtuous cycle in which post-evaluation findings are fed back into future PPP appraisal and management processes.